EV Charging Without a Driveway: Apartments, Strata and Kerbside Options
No driveway, no problem, mostly: what strata law lets you install, which kerbside chargers exist, why the footpath cable is a dead end, and how to get a charger on your street.

On this page
Charging an EV without a driveway comes down to four options, in the order you can realistically have them: public charging near places you already park, including JOLT’s free 7 kWh a day; a charger in your building’s car park if you live in an apartment, which strata law in several states now makes hard to refuse; a kerbside or pole-mounted charger on your street, which charge point operators are installing by the hundred on council land and distributor poles; and a cable from your house to the kerb, which almost no council permits. About one in three NSW drivers has no off-street parking, and the money to fix that is finally moving. This guide covers each option, what is funded near you, and how to ask for a charger on your street.
Can you get a charger in your apartment building?
If you own an apartment with a car space, this is the option worth the most effort, because it turns public charging into home charging. It is also the one with the most paperwork: a charger in a strata car park almost always runs cable through common property, so it needs the owners corporation’s approval. The rules differ by state.
New South Wales. EV charging counts as sustainability infrastructure under the Strata Schemes Management Act, so a resolution to install it passes unless 50 per cent or more of the votes cast are against it, not the 75 per cent a special resolution needs, and since 2025 a by-law cannot block a charger on appearance grounds. A further bill would give a lot owner a standalone right to install a charger, down to a plain 10-amp socket, with three months for the committee to object in writing and NCAT as the referee; it passed the Legislative Assembly and, as of September 2026, was still before the Legislative Council, so check NSW Fair Trading for whether it has commenced. The NSW EV-ready strata pages carry example motions and by-laws. Tenants cannot apply directly; the landlord applies for you.
Victoria. No EV-specific voting rule; changes to common property go through the owners corporation under the Owners Corporations Act 2006. Since August 2026 the state has a detailed EV-ready guide for owners corporations covering capacity, cost-sharing and approvals. Attach it to your request.
Queensland. A charger that connects to common property wiring needs body corporate approval. The committee can approve it if the total cost, including installation, is under $3,000 and it does not detract from the building’s appearance; above that it needs an ordinary resolution at a general meeting. The Body Corporate and Community Management office has a fact sheet.
ACT. Sustainability infrastructure on common property needs only an ordinary resolution, and an owners corporation’s rules cannot prohibit it. Since 27 September 2024 the Territory Plan has required every new multi-unit development to be EV-ready to every unit’s car space; the ACT Government’s guide covers retrofits.
Elsewhere. WA, SA, Tasmania and the NT have no EV-specific strata rule as of September 2026; ask your strata manager what resolution a change to common property needs.
Two things help everywhere. The National Construction Code has required new apartment buildings to be built ready for EV charging since 2024, and the ACT’s pilot study of existing buildings found most needed no supply upgrade once load management was fitted, which answers the committee member who says the building cannot take it. The federal energy.gov.au toolkit has the survey and quote templates a committee will ask for; the hardware is in our EV charger installation guide.
What already exists on Australian streets?
Four models are in the ground, run by different people on different money.
| Model | Who runs it | Speed | What you pay |
|---|---|---|---|
| Advertising-funded kerbside DC | JOLT | 25 or 50 kW DC | First 7 kWh a day free plus a service fee; rate past that shown in the app |
| Pole-mounted kerbside AC | EVX nationally, plus Chargepost and PlusES on Ausgrid poles in Sydney; in Melbourne, CitiPower, Powercor and United Energy own trial units that Zuup, WeVolt and Chargefox operate | 22 kW AC, two sockets, BYO Type 2 cable | Per kWh through the operator’s app |
| Council car park AC | Councils, usually through Chargefox or Exploren | 7 to 22 kW AC | Set by the council; sometimes free |
| DC fast charging nearby | Chargefox, Evie, BP Pulse, Ampol, Tesla | 50 to 350 kW | Per kWh; the dearest electricity an EV buys |
JOLT is the one built for you. Its chargers double as advertising panels, and the ad revenue pays for the first 7 kWh every driver takes each day, about 45 km in roughly 15 minutes. As of mid-2026 it runs roughly 100 sites, concentrated in Sydney, Melbourne and Adelaide. The discipline is plugging in for a quarter of an hour every time you pass one; our JOLT guide covers the fees and the app.
Pole-mounted chargers are growing fastest, because they bolt onto a power pole that already carries electricity: no trench, no cabinet on the footpath. Every unit is 22 kW AC with two Type 2 sockets and no cable, so carry your own (seven metres is the sensible length). Most cars draw 7 to 11 kW on AC, so a full charge is an overnight or working-day job. Most are owned and run by a charge point operator on a pole it rents from the distributor: EVX had 100 in NSW by mid-2025 with 120 more planned, on RACV’s count. The distributors are regulated monopolies and cannot sell charging themselves, so in Sydney Ausgrid passes nominations to Chargepost, EVX and PlusES and estimates its area needs 11,000 kerbside chargers, and the 47 going up in The Hills, Parramatta and Blacktown sit on Endeavour Energy poles with Endeavour fitting the metering and an operator selling the charging. Melbourne is the exception: CitiPower, Powercor and United Energy hold a regulator’s waiver to own up to 100 trial units, which Zuup, WeVolt and Chargefox operate, so one unit works with any of those apps; 33 sites were live across Fitzroy, Richmond, Hawthorn and Kew as of September 2026. Bays are usually signed “EV only while charging” with a three- or four-hour limit, so read the sign.
Council car park chargers are the quiet workhorse: 7 to 22 kW posts behind the shops, often the cheapest paid charging in the suburb and occasionally free; our free charging directory lists the genuinely free ones. DC fast charging is the fallback, not the plan: a weekly 20-minute session keeps a city car going at the highest price per kilometre of any option. The map finds the nearest and the public charging guide explains the apps and prices.
Can you run a charging cable across the footpath?
Mostly no, and the councils that tried to allow it have backed away. City of Yarra puts it plainly: it does not permit electrical cables on or above footpaths, and any that appear are subject to enforcement action. That is the common position, written down or not.
The exceptions are trials, and three are worth knowing. City of Port Phillip has run the longest, since November 2022, and now permits three technologies: a pop-up charger in the kerb, a recessed cable channel across the footpath, and a boom over it. It runs until mid-2028 or 100 chargers; 22 were in by May 2026 on the council chief executive’s count. The brake is probably the paperwork, all of it on the resident: about $500 to apply, annual fees, a bond, $20 million of public liability insurance, and no exclusive bay at the end. Inner West Council in Sydney issued a handful of covered-cable permits from September 2023, then told Yahoo News it was no longer actively supporting the practice, on safety grounds. Merri-bek City Council in Melbourne’s north is running the boom-only version: 30 households with no off-street parking have a pole in the front garden carrying a retractable boom 2.5 metres above the footpath, so the cable never touches the ground. Only property owners could apply, heritage streets were excluded, participants pay for the gear and the permit, and the trial that began in September 2025 is closed to new applicants and under review until September 2026.
The legal footing is the same across Victoria. A footpath is part of the road, and section 63 of the Road Management Act 2004 says nobody may carry out works in, on, under or over a road without the council’s written consent, so a boom swinging a cable above the footpath needs a yes before it goes up, and a council that does not want one simply withholds it. Section 121 of the same Act is how a council says yes: an enforceable agreement with the owner of the house that sets out who pays, who maintains the gear and who carries the risk, which is why the trials come with application fees, a bond and public liability cover rather than a plain approval.
So: do not run a lead across the footpath without a written permit. You carry the liability if someone trips, and a domestic extension lead is the wrong equipment for hours of full-current charging anyway, as our extension cord guide explains. Ask your council’s transport or sustainability team, in writing, whether it permits covered cables, recessed channels or booms. If the answer is no, that email starts your case for a public charger on the street instead.
What is already funded near you?
The money may already be allocated to your area, which turns the ask from “please fund this” into “please use the funding”.
New South Wales is furthest along. The state’s kerbside charging program is $10 million across multiple rounds, targeted by a priority map at the suburbs with the least off-street parking. Round 1 allocated $4.1 million to 671 charge ports across 391 sites in 16 council areas; round 2 offered $4.5 million and closed in December 2024. Only charge point operators could apply: the operator applies, the council licences the bay. The 2026 NSW EV Strategy, released in April 2026 with $100 million behind it, names kerbside chargers for apartment residents as one of five priorities.
Nationally, ARENA is co-funding EVX’s ChargeKonnect project: $2.43 million towards 250 pole chargers across council areas in NSW, Victoria and South Australia to February 2028, with every major distributor in those states as a partner. The federal government’s Accelerating EV Charging Program is the bigger pot: $40 million announced in September 2025, mostly grants to the electricity distributors, who pick the poles with councils and operators. Kerbside AC on existing poles in metropolitan and major regional centres comes first, with grants due in December 2026 and installs from March 2027, subject to a pending change to the national electricity rules. One catch, from the program’s council guidance: there is “no expectation” that a distributor-installed charger comes with a dedicated EV bay, so the bay is a separate ask to your council. The program’s other half is regional: the same mapping tool names 336 country towns for new fast chargers by 2034, and our regional blackspots page shows which of them still have none listed.
Victoria has the distributor trial above, 100 chargers running until 2031, and RACV’s partnership with EVX, announced in July 2025, for up to 40 dual chargers starting in Ashburton with Port Phillip, Stonnington and Yarra next.
If your council area is on the NSW priority map, inside the CitiPower, Powercor or United Energy footprint, or in an EVX partner network, a charger on your street is a matter of nomination and licence, not money.
How do you ask for a charger on your street?
Four routes, in order of how much they move things. Use them together.
1. Nominate a pole. The fastest and least known. In Sydney, the Central Coast and the Hunter, Ausgrid asks residents to send a street address and pole number to one of its operators, Chargepost, EVX or PlusES. EVX takes requests for any Australian address through a form that asks only for your name, email and the address. In Melbourne, the CitiPower and Powercor engagement page still takes feedback although its consultation closed in February 2026. You do not need to own the property to nominate a public pole. Nominate with neighbours, not alone: a request signed by several households on the street, including whoever lives beside the pole, is what gets one site picked over the next, and later a signed bay. Not every pole is suitable, so name two or three.
2. Your council’s consultation. When a council proposes chargers it runs a Have Your Say with a map, a survey and a deadline of a few weeks. Bayside’s ran from 4 March to 21 April 2024; Inner West’s 2026 round went to its Local Transport Forum on 18 May and was decided by Council on 16 June. Subscribe to your council’s engagement site now, because the loudest voices in a short window are usually the people who do not want a bay outside their house.
3. The budget submission. The strongest ordinary-resident lever, and it is date-gated: NSW councils must exhibit their draft operational plan for at least 28 days before adopting it for the year starting 1 July, and Victorian councils must adopt the budget by 30 June after community engagement. Ask for something specific and cheap: an EV charging strategy, a template licence agreement for charge point operators, or a named car park. The JOLT model costs a council nothing but parking bays, so the ask is permission, not money.
4. Petition and speak. Most councils let residents address a meeting and accept petitions; thresholds vary. Forty signatures from one street prove demand at a site in a way a thousand online signatures do not.
Worked example: how Bayside got its kerbside chargers
Bayside City Council, in Melbourne’s south-east, is useful because one council ended up with five commercial models, on different money, in about two years.
JOLT proposed nine 50 kW stations in the council’s shopping precincts, each converting up to two parking bays, installed and operated at no cost to council and funded by the advertising panel on each unit. Council put the nine sites on its Have Your Say page with a map and a plain FAQ from 4 March to 21 April 2024. Six sites were supported. The first charger, at the Black Rock car park on Balcombe Road, went live in November 2024; Highett followed in March 2025, Beaumaris in June 2025, then Cheltenham, with Sandringham planned for 2026.
Around it, per the council’s project page: two Evie chargers at Brighton, upgraded to 50 kW; three Exploren chargers at the council’s own Corporate Centre, installed in February 2026; EVX pole chargers due in 2026 and 2027; and the older Chargefox 22 kW posts. Council’s contribution was parking bays, signage and process. That is the pattern to point your own council at.
Templates you can copy
Fill the brackets and keep it short; the ones with a pole number and a count get answered.
A. Site nomination to a distributor or operator
Subject: Pole charger nomination, [street], [suburb] [postcode]
I am nominating the pole outside [number] [street], [suburb], pole number [from the pole, or “not visible”], for a pole-mounted EV charger. The street has [number] dwellings with no off-street parking and [number] EVs already park on it overnight. The nearest public charger is [name], about [distance] away. [Number] neighbours, including the household beside the pole, support this and are listed below. I am happy to be contacted. [Names, emails, phone]
B. Council submission
Subject: Kerbside EV charging in [suburb]: a site and a licence pathway
I live at [address], in a street where [most / many] homes have no off-street parking, so residents cannot charge an EV at home. I ask Council to (1) nominate [car park or street] as a kerbside charging site and (2) adopt a licence agreement that lets a charge point operator install at no cost to Council, as Bayside City Council has done with JOLT. [NSW: our suburb is in a priority zone of the NSW kerbside grants.] [Ausgrid area: the distributor passes pole nominations to its charge point operators. CitiPower / Powercor areas: the distributor is installing pole units for operators to run. Council’s role is the bay.] Could you tell me within 28 days which officer holds this and whether a consultation is planned? [Name, address, email]
C. Budget submission paragraph
I ask Council to include in the [year] budget an EV charging strategy covering kerbside and car park charging for residents without off-street parking, and a template licence agreement for charge point operators, so operator-funded chargers can be installed without Council capital. About [share] of households in [suburb] have no off-street parking. State, ARENA and federal money is already flowing to kerbside charging; Council’s part is permission and process.
D. Questions to ask a provider before you support a site
Who pays for installation, electricity, maintenance and removal? What does a session cost, including any connection or idle fee, and where is that published? What are the bay’s parking restrictions and who enforces them? What is the contract term with Council, and what happens to the charger if the operator fails? Does the charger work with other apps? How is uptime reported, and to whom?
What to expect
Eight months from consultation to the first charger is the good outcome; Bayside managed it because JOLT arrived with a funded proposal and the council only had to run the process. Two years for a set of sites is normal. An operator with its own funding moves fastest, which is why the EVX form is route one. Distributor-owned trials are the slow lane: CitiPower and Powercor consulted in November 2025, had their first chargers running in March 2026, and in August 2026 the regulator extended their deadline for picking sites.
The delays are structural: a charger on a pole needs the pole owner’s agreement, the connection, a council licence for the bay and a traffic committee sign-off. A distributor that wants to own the chargers itself also needs a ring-fencing waiver from the Australian Energy Regulator, because it is a regulated monopoly that must not compete with the operators it rents poles to. Your nomination, consultation response and budget submission move your site up that queue. Meanwhile the map shows what is within walking distance, and 15 minutes at a JOLT charger covers a day’s driving for most people.
Frequently asked questions
Can you charge an EV if you live in an apartment?
Yes, with planning. If you own a car space, a charger in the building is the best long-term answer: New South Wales and the ACT let owners corporations approve EV charging with an ordinary majority, and Queensland lets the committee approve installs under $3,000. If your building will not move, kerbside chargers and JOLT's free 7 kWh a day cover most city driving, and public fast charging fills the gaps.
Can strata refuse an EV charger in Australia?
It depends on the state. In NSW a resolution to install EV charging passes unless 50 per cent or more of votes cast are against it, by-laws cannot block a charger on appearance grounds, and a bill before Parliament as of September 2026 would give owners a right to install one that the committee can only object to in writing within three months. The ACT needs only an ordinary resolution. Queensland and Victoria decide case by case under general strata law, so a well-prepared application matters.
Can I run an EV charging cable across the footpath?
Almost never without a permit, and most councils do not issue one. City of Yarra, for example, does not permit cables on or above footpaths and treats them as an enforcement matter. Inner West Council in Sydney trialled covered-cable permits and stepped back on safety grounds, and Merri-bek is trialling an overhead boom with 30 households. Ask your council in writing before you plug anything in across public land.
How do I get an EV charger installed on my street?
Nominate a power pole. In Sydney, Ausgrid sends nominations to its operators Chargepost, EVX and PlusES; EVX takes requests for any Australian address on its website. Then use your council's consultation when it opens and its annual budget submission, which in NSW and Victoria runs in the months before 30 June. Bayside City Council went from consultation to its first kerbside charger in eight months.
Is kerbside EV charging free?
Only JOLT's is, and only the first 7 kWh a day, about 45 km of range, with a small service fee per session. Pole-mounted 22 kW chargers, whether EVX's or the ones on CitiPower and Powercor poles in Melbourne, are paid per kWh through the operator's app, and you bring your own Type 2 cable. Council car park chargers are sometimes free; our free charging directory lists the ones that are.